Public Radio for Alaska's Bristol Bay
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

State delays renewal of Pebble land use permit

State of Alaska DNR

Citing high number of public comments to log and review, DNR has extended the current permit by three months but delayed deciding on full two year renewal.

Alaska’s Department of Natural Resources has delayed renewing a two year land use permit for the Pebble Limited Partnership to give state regulators more time to review an “extensive” number of public comments.  KDLG’s Dave Bendinger has more:

Audio Transcript: The state issued miscellaneous land use permit (MLUP) will allow Pebble to continue exploration activities at its claims northwest of Iliamna. The company acknowledges little is planned for the upcoming field season and little has occurred there since losing the financial backing of partner Anglo American in 2013. Pebble says it is operating the claims under ‘care and maintenance’ status, but still needs to the land use permit to do so.  

While it's considered a routine renewal of a permit that does not allow for any large scale mining, Pebble is a uniquely controversial project, and critics took a public comment period to raise "substantive" issues.

"Normally we don’t have the number of comments come in for a permit application that came in for this one," said Marty Lentz, the Mining Section Chief within DNR’s Division of Mining, Land, and Water. "The timeframe of those comments, and the importance of the project, require us to give substantial time to review and thoroughly examine the comments and consider how important they are to implement any opportunities within the permit for those suggestions."

DNR sent a letter to Pebble explaining the extension of the current permit in order to delay action on the full two year renewal request. The Department "received many substantive comments on some complex issues," the letter says, and the delay will allow staff to "comprehensively consider the breadth and scope of the complex issues raised" during the public process.

Lentz says his office is still logging all of the input, and offered no comment on any specific concerns raised. 

Many public comments were sent in regardinga report commissioned by the United Tribes of Bristol Bay and conducted by geophysicist Dave Chambers. Last summer Chambers traveled around the Pebble claims to survey a portion of the exploratory well sites; his report was critical of drill cuttings left exposed on the tundra, well casings left sticking above the surface, and some drill holes that were allowing water to flow out. Chambers believe some of those issues, specifically the drill cuttings, have not been as concerning to state and federal regulators as they should be.

"I’ve reviewed the report by Mr. Chambers, and there will be opportunities in the upcoming field season during our inspection to answer the accuracy of the statements in that report," Lentz said.

The public comment period on the permit renewal was open for 30 days in November. That, says Lentz, is also unique, tied to a lawsuit brought by Nunamta Aulukestai against DNR.

“The Nunamta court case required a 30 day comment period on permit applications period [be given] to the plaintiffs in that court case. Our standard practice for these permits has been a courtesy public notice for 14 days, but we’ve granted that [30 day] comment period to the public as well as the plaintiffs in that court case.”

DNR extended Pebble's current miscellaneous land use permit for three months while it reviews the public comments. Pebble is still seeking the full two year renewal for 2017-2018 activities.

PLP says it maintains a "clean and compliant" mineral exploration site, something the state regulators at DNR tend to agree with. They inspect the site every year, and in their most recent reportfrom the 2016 season say "overall, the Pebble Limited Partnership operation is in good condition and is consistent with industry standards."